Upcoming Projects

CONSTRUCTION

CONSTRUCTION SPECIFICATIONS:

DESIGN
ARCHITECT DESIGN AS PER VASTHU
FOUNDATION
EARTHWORK EXCAVATION FOR ISOLATED FOOTINGS AND FOR THE PLINTH BEAMS AS PER STRUCTURAL DRAWINGS.

BASEMENT
BRICKWORK IN CEMENT MORTAR 1:5 MIX WITH CHAMBER BURNT BRICKS OF 1ST SORT TO A HEIGHT OF 2’6’’ FOR THE FLAT AREA FROM THE ROAD LEVEL.

ELECTRICAL
THREE-PHASE ELECTRICAL WIRING CONCEALED SWITCHES ALL AS PER NECESSARY REQUIREMENTS TO BE SUPPLIED INCLUDING PROPER EARTHING AND INVERTOR LINES ALSO PROVIDED.
STRUCTURE
RCC STRUCTURE WITH 9’’ BRICK EXTERNAL WALLS AND 41/2’’ BRICK PARTITION WALL.
PLASTERING
CEILING, INNER & OUTER WALLS PLASTERING IN CEMENT WITH NEAT FINISH.
KITCHEN
20 MM BLACK GRANITE COUNTER WITH STAINLESS STEEL SINK WITH DRAINBOARD WILL BE PROVIDED.

JOINERIES
MAIN DOOR FRAME AND SHUTTER WITH TEAK WOOD & VARNISH FINISH. OTHER DOORS PADAK WOOD FRAME SIZE OF 4’’X21/2’’

ALL WINDOWS WITH PADAK WOOD FRAME, SIZE OF 4’’X21/2’’ AND SHUTTERS WITH PADAK WOOD, SIZE OF 3’’X11/2’’ WITH 4MM PINNED GLASS.FULL PUTTY FINISH WITH 2 COATS OF ENAMEL PAINT OVER ONE COAT OF PRIMER.
LOFTS
2’ WIDE, ALONG ANY ONE SIDE OF THE BEDROOMS AND KITCHEN.

PLUMBING
CONCEALED CPVC PIPELINE IN BATHROOM, PVC PIPES FOR RAINWATER, SANITARY WASTE.
FLOORING
ROOMS: VITRIFIED TILES OF SIZE 2’X2’ OVER THE ENTIRE AREA (EXCEPT TOILETS)
TOILETS: CERAMIC ANTISKID TILES OF SIZE 12’’X12’’ FOR THE TOILET FLOORING.

PAINTING
INSIDE WALLS AND CEILING WITH CEMENT BASED PUTTY FINISH WITH TWO COATS OF INTERIOR EMULSION OVER ONE COAT OF PRIMER.
OUTSIDE WALLS TWO COATS OF EXTERIOR EMULSION ONE COAT OF WHITE CEMENT.
WARDROBE
WARDROBE OF ONE NUMBER WITH 4’ WIDTH, 1’9’’ DEPTH AND 3 SHELVES WITH CUDDAPAH SLABS.
TERRACE
PARAPET WALL : BRICK WORK OF 4.5 THICK WITH CEMENT MORTAR 1:4 MIX TO A HEIGHT OF 3’6’’ WITH 9’’ THICK BRICK PILLARS AT EVERY 9’ INTERVAL.

PAYMENT DETAILS
ADVANCE PAYMENT – 20%
COMPLETION OF PLINTH BEAM – 10%
COMPLETION OF BASEMENT – 15%
COMPLETION OF ROOF WORK – 15%
COMPLETION OF BRICKWORK – 15%
COMPLETION OF PLASTERING – 10%
COMPLETION OF FLOORING – 10%
COMPLETION OF PAINTING – 5%